Ptr Brothers Projects v. the State of Andhra Pradesh
Contractual dues – non-payment of bills for completed works
Case brief
What is this about?
Ptr Brothers Projects v. The State of Andhra Pradesh and Others, WRIT PETITION NO: 32779/2025, High Court of Andhra Pradesh at Amaravati (Special Original Jurisdiction), decided 21.07.2026 by Ravi Cheemalapati, J. Contractor's writ petition aggrieved by non-payment of bill amounts for completed works; Government Pleader/Assistant Government Pleader (Roads & Buildings, Sri Abdul Rasheed) conceded payment of net amount after statutory deductions and sought six months; petitioner's counsel (Shaik Jahangeer Basha) had no objection; court disposed of the petition at admission stage directing release of the legally admitted/entitled net amount within six months, reserving interest claims to an appropriate forum; no costs. Keywords: unpaid bills, completed works, statutory deductions, six-month payment direction, disposal at admission stage, interest left open. No statutes or precedent cases cited; no monetary figures disclosed.