M/s. Sri Sainath Infra Projects v. The State of Andhra Pradesh
Case brief
What is this about?
Andhra Pradesh High Court at Amaravati, Writ Petition No. 15770 of 2026, decided 20.07.2026 by Justice Ravi Cheemalapati. M/s. Sri Sainath Infra Projects (contractor) vs State of Andhra Pradesh (R&B and Finance Departments), Engineer-in-Chief, Superintending Engineer and Executive Engineer (R&B NH Division, Vijayawada). Subject: release of admitted work bills of Rs.5,88,855/- and Rs.6,08,231/- under Agreement Nos. DR.No.08/2023-2024 and DR.No.9/2023-2024 dated 12.03.2024; Budget/LOC allocation request; payment through NIDHI portal by PAO; mandamus under Article 226; disposal at admission stage with consent of both parties; three months' time for payment; interest at 18% claim left open to be agitated in appropriate forum; no costs; IA under Section 151 CPC closed. No precedents cited; single-judge Bench.
What did the court decide?
Respondent authorities directed to pay Rs.5,88,855/- and Rs.6,08,231/- to the petitioner within three months from receipt of a copy of the order; petitioner left free to agitate interest claim in an appropriate forum; no order as to costs; pending interlocutory applications closed.