Sri. S. Leela Mohan Reddy v. he State of Andhra Pradesh
Writ Petition under Article 226 – Non-payment of contractor's dues
Case brief
What is this about?
Andhra Pradesh High Court, W.P. No.15556 of 2025 (Harinath.N, J., 13.08.2025): S. Leela Mohan Reddy v. State of A.P. and others — contractor sought a writ of mandamus for release of Rs. 9,75,406/- withheld despite finalized bills for CC road upgradation works under Gadapa Gadapaku Mana Prabhutvam (Agreement No.540/GGMP/EEI/2023-24, dated 17.01.2024), with interest @ 24% per annum; the Court directed respondent Nos. 3 to 5 (Nellore Municipal Corporation, Executive Engineer and Finance & Planning Department) to verify and release the dues within six weeks; petition disposed of, no costs. Keywords: Article 226 mandamus; municipal works contractor payment; M-Book certification; release of pending bills; Section 151 CPC application.
What did the court decide?
Direction to respondent Nos. 3 to 5 to verify and release the payments due and payable to the petitioner as expeditiously as possible, preferably within six (06) weeks from receipt of a copy of the order; writ petition disposed of with no costs.