S Leela Mohan Reddy v. the State of Andhra Pradesh
Case brief
What is this about?
Writ of Mandamus Article 226; non-release of undisputed contractor bills Rs. 19,36,697/-; Nellore Municipal Corporation; Gadapa Gadapaku Mana Prabhutvam works; Agreement no.541/GGMP/EEI/202324 dt.17.01.2024; counter-affidavit admits dues undisputed; direction to verify and release payment within four weeks; disposed of, no costs; interest claim in prayer not reflected in operative order; Justice Harinath.N; decided 12.08.2025.
What did the court decide?
Direction to the respondents to verify and release the payments due to the petitioner as expeditiously as possible, preferably within four (04) weeks from receipt of a copy of the order; writ petition disposed of with no costs; pending miscellaneous petitions, if any, stand closed. (The prayer for interest @ 24% p.a. finds no corresponding direction in the operative order.) ¶36