S Leela Mohan Reddy v. the State of Ap
Case brief
What is this about?
Writ petition (mandamus, Article 226) by contractor S Leela Mohan Reddy against State of Andhra Pradesh, District Collector SPSR Nellore, Nellore Municipal Corporation, Executive Engineer and Principal Secretary Finance & Planning for release of withheld payment of Rs. 10,92,589/- for CC road work under Gadapa gadapaku mana prabhutvam, Agreement No.545/GGMP/EEI/2023-24 dated 17.01.2024; bills finalised, M-Book certification; direction to respondent Nos. 3-5 to verify and pay within six weeks; Section 151 CPC IA; disposed of, no costs; interest @24% claimed but not granted; Justice Harinath.N, dated 13/08/2025.
What did the court decide?
Writ petition disposed of with a direction to respondent Nos. 3 to 5 to verify and release the payments due to the petitioner as expeditiously as possible, preferably within six (06) weeks; no costs; pending miscellaneous petitions, if any, stand closed. The prayer for interest @ 24% per annum was not specifically dealt with in the operative directions.