M/s. Balaji Energy Pvt. Ltd, v. The Southern Power Distribution Company of A.P Limited
Case brief
What is this about?
A mini-hydel generator sought unpaid electricity charges and interest under a final regulatory order. The court held the implementation writ maintainable and the enhanced capacity's commercial operation date settled. It allowed the petition, permitting an updated claim and directing payment of legally entitled dues within three months of receipt.
What did the court decide?
Liberty to submit an updated dues representation within two weeks; respondent directed to pay legally entitled dues under the APERC order within three months of receipt.