Thirumala Constructions v. the State of Ap
Case brief
What is this about?
This writ petition challenged the withholding of Rs. 96,52,030/- contract dues. The respondent admitted the claim but sought three months for fund clearance. The Court disposed of the petition and directed the release of the amount within three months.
What did the court decide?
The respondents are directed to release the balance amount to the petitioner at the earliest, but absolutely within a period of three months from the date of receipt of this order's copy.