Maramreddi Chiranjeevi Reddy v. The a.P.Southern Power Distribution Company Limited
Case brief
What is this about?
A single judge disposed of a writ petition challenging the initiation of power supply disconnection notices for aqua cultural farms. Pending consideration of the petitioners' explanations and in view of pending proceedings, the court directed the authority to consider the reply and maintain status quo.
What did the court decide?
Direction to the Assistant Executive Engineer to consider the petitioners' reply dated 14.07.2021 and decide within four weeks. Status quo maintained on service connections.