M/S Et Infra Developers Pvt. Ltd. Thru. Authorized Signatory Ms.Shiwanjali Pandey v. State of U.P. Thru. Addl. Chief Secy. Deptt. Infrastructure/Industrial Development and 3 Others
Case brief
What is this about?
Maintainability of review against revisional order under Section 41, U.P. Urban Planning and Development Act, 1973; State Government decision 27.03.2025 — no review power against Section 41 revisional orders; NOIDA board resolution no.214/50 dated 12.07.2024 (agenda no.50, 214th board meeting) seeking review of final order dated 28.03.2024 in Revision No. 1922/77-4-24/Appeal 89/23; follows/applies earlier order in Writ-C No.7009 of 2024 dated 11.04.2025; M/S Et Infra Developers Pvt. Ltd. v. State of U.P.; WRIT-C No. 8807 of 2025; Pankaj Bhatia, J.; petition disposed with three-month window for lawful steps, else implementation of revisional order.
What did the court decide?
Petition disposed of in terms of the Court's earlier order in Writ-C No.7009 of 2024: the decision to prefer a review is not to be acted upon; the respondent authority may take such steps as are advised under law within three months, failing which the revisional order dated 28.03.2024 shall be implemented in accordance with law.