Shaikh Akhtarunnisha Mohammad Shekhawat v. U.P. Power Corp. Ltd. Thru. Chairman Lko. and 3 Others
Case brief
What is this about?
electricity connection dispute; U.P. Power Corp. Ltd.; writ petition WRIT - C No. - 251 of 2025; Aakash Gupta; premises dispute; counter affidavit and rejoinder directed; supplementary affidavit taken on record; interim order pending; High Court of Judicature at Allahabad, Lucknow Bench; Rajan Roy and Manish Kumar, JJ.; Order Date 22.1.2025.
What did the court decide?
No substantive adjudication at this stage. The Court took the petitioner's supplementary affidavit on record, directed the opposite parties nos. 3 and 4 to file a counter affidavit within three weeks detailing the dispute concerning the premises and the person raising it, permitted a rejoinder affidavit within one week thereafter, and ordered the matter to be listed thereafter. ¶9