Barat Kumar Lakhmani v. U.P. Electricity Regulatory Commission Lucknow and Another
Case brief
What is this about?
Allahabad High Court; WRIT-C 12637 of 2025; Barat Kumar Lakhmani; U.P. Electricity Regulatory Commission; new electricity connection mandamus; OK Connection Feasibility Status Report; SDO and JE; representations ignored by respondent no.2; Executive Engineer EUDD Kalyani Devi 1 Kamla Nehru Road Prayagraj; disposal without merits; fresh representation within 15 days; decision within one month with hearing; Saral Srivastava J.; Sudhanshu Chauhan J.; November 13, 2025.
What did the court decide?
Permission to file a fresh representation alongwith certified copy of the order raising all grievances before respondent No.2-Executive Engineer, EUDD, Kalyani Devi, 1 Kamla Nehru Road, Prayagraj within fifteen days; respondent No.2 to consider and decide it in accordance with law after providing proper opportunity of hearing within one month of receipt.