Md. M.A. Naseeb Khan v. The State of Telangana
Case brief
What is this about?
Telangana High Court (Surepalli Nanda, J.) W.P. No. 34046 of 2024 decided 02-01-2025: contractor's mandamus petition under Article 226 for settlement of final bills (~Rs. 34,00,000/-) for repairs and renovation to GHS NBT Nagar, Gowliguda/Banjara Hills/Shaikpet, Hyderabad, under MOMB-MBMB Scheme (Samagra Shiksha), agreement No. 48 of 2022-23 dated 20.01.2023; writ disposed of with direction to conclude settlement steps within 8 weeks as per lawful entitlement; no costs; Section 151 CPC application; no precedent cited or discussed.
What did the court decide?
Direction to the respondents to conclude the steps already initiated for settlement of the petitioner's final bills for the subject work within eight (08) weeks from receipt of copy of the order as per the petitioner's lawful entitlement; no order as to costs; pending miscellaneous petitions closed.