Ballem Venkateswarlu v. Smt. Bhukya Aruna
Case brief
What is this about?
Telangana High Court closes contempt case; Sections 10-12 Contempt of Courts Act; directions dated 03-12-2024 in W.P. No. 31307 of 2024 on illegal construction by 6th respondent; respondent Secretary, Danthelabora S.C. Grampanchayat; notices 27-01-2025; proceedings dt.03.02.2025; compliance with delay, not non-compliance; parties own brothers, 20-year land dispute; non-tribals; Survey Nos. 242-243 under Act 1/70 of Agency Area; no construction permission; parties directed to civil/Agency Court; aggrieved parties free to challenge proceedings; Contempt Case closed at this stage; Justice T. Madhavi Devi.
What did the court decide?
Since the respondent issued notices to both the parties and issued proceedings dated 03.02.2025 pursuant to the Court's directions, this is not a case of non-compliance but a case of compliance with delay.