This judgment disposes of a writ petition challenging the respondent power company's refusal to adjust 50% of penal charges collected. The petitioner sought a direction to accept the adjustment and prohibit power disconnection. The court found that the cause of action no longer survived as the adjustment had been credited in March/April 2014, per respondent affidavits.
What did the court decide?
The writ petition was closed due to extinction of cause of action; no order as to costs.