M. Srinivasa Reddy v. Southern Power Distribution Company Ltd.
Case brief
What is this about?
The High Court disposed of a writ petition seeking a mandamus for an electricity connection. The petitioner claimed the respondent failed to process his application under Section 43 of the Electricity Act, 2003. The Court directed the respondents to consider the application within four weeks.
What did the court decide?
Directed respondents to consider the application filed by the petitioner dated 06.01.2023 and provide power supply or pass appropriate orders within four weeks.