M/s. Indu Projects Limited, v. Telangana Micro and Small Enterprises Facilitation Council
Case brief
What is this about?
A supplier's payment award was set aside because the Facilitation Council bypassed statutory conciliation and gave no reasons. The Court entertained writ review despite the statutory remedy, upheld the supplier's entitlement to invoke the MSMED Act on these facts, and remitted the claim for conciliation and, if necessary, arbitration within 90 days.
What did the court decide?
Council's award set aside; claim remitted for statutory conciliation and, if unsuccessful, arbitration, with a reasoned decision within 90 days of receipt of the order.