the proper coordination of works that a Telegraphic Authority possessed under the provisions of the Indian Telegraph Act, 1885 (Central Act No.13 of 1885); that in exercise of the said power, the 1st respondent, viz., A.P. Transco, had approved a scheme by the Chief Engineer vide letter dt.10.02.2017 for extension of 50M.W. (55.56M.V.A.) power supply for pumping of Kondaveetivagu flood water into Prakasam barrage at Guntur District with an estimate cost of Rs.50.63 crores (power transmission works); that the Indian Electricity Act was repealed and in its place, new statute, i.e., the Electricity Act, 2003 was enacted and there is no provision to obtain prior consent from the owners of the property for laying electricity lines; that the Supreme Court in Power Grid Corporation of India Limited v. Century Textile and Industries Ltd and others2 upheld the power of the Electricity Companies to lay the towers and lines without prior consent of the owner; that in fact, the Assistant Engineer, TLC Sub-Division-I of A.P.TRANSCO at Guntur has issued a notice to the petitioner through Registered Post informing that a tower is going to be constructed in its land bearing Sy.No.324 and further informed that the compensation as fixed by the revenue department will be paid; and that the said notice was returned