(Yellampally), Anthargram Mandal, Peddapally District to Medigadda Pump House near Kaleshwaram. That the purpose of the said project is to lift water by pumping from Medigadda barrage to Yellampally and that for the said purpose electricity line has to be laid to provide power to the pump house. That administrative approval was accorded vide T.O.O.168, dated 08.12.2016 for erection of towers and stringing of lines and the route approval was also given by proceedings dated 21.07.2016 and already foundation of 91 towers have been completed. It is stated that notice was already issued to the petitioner informing him that the 220 KV power transmission line shall pass through the property and a tower shall also be erected for which compensation for the crop loss shall be paid as per the procedure. It is stated that there is no need to obtain consent of the petitioner as land owner, by virtue of judgments reported in Sri K.Subba Raju vs. Executive Engineer, TLC Division, AP Transco [2010 (4) ALD 358], G.V.S.Rama Krishna v. A.P.Transco, [2009 (3) ALD 343], Devisetty Ramaswamy vs. Chief Engineer, 400 KV Line, AP Transco, Hyderabad [2013 (4) ALD 88], Bommi Reddy Narasimha Reddy v. Power Grid Corporation of India Ltd., Proddatur, YSR Kadapa & others [2014 (1) ALD 697] and also order of the Hon’ble Supreme Court dated 14.12.2016 in Civil Appeal No.10951 of 2016.