What is this about?
In this revision petition challenging the return of a claim petition under Order 21 Rule 97 CPC, the Court held that the timing was not ripe. The petitioner was directed to re-present papers clarifying maintainability, and the executing court was directed to pass a judicial order on the question before the revision could be revisited. Thus, the revision was dismissed.
What did the court decide?
The Civil Revision Petition is dismissed; the petitioner is directed to re-present papers, and the Court below directed to pass a judicial order on maintainability.