M/s. Sri Hari Feerow Alloys (P) Ltd, (S.C. No Nsb 298) v. The Southern Power Distribution Company, Of
Case brief
What is this about?
The Court held that Section 47(5) of the Electricity Act disqualifies distribution licensees from demanding security if a consumer opts for a pre-paid meter. It directed licensees to install meters for all interested HT consumers within six months and regulated interim deposit payments until installation.
What did the court decide?
Directing respondents to install pre-paid meters within six months; petitioners to pay half the demanded deposit until installation, refundable upon meter installation.