M/s. Coramandal Prestcrete (Pvt) Ltd. v. Engineer-in-Chief
Case brief
What is this about?
This appeal allowed a civil contractor to recover unpaid amounts and security deposits from a government department. The court held the notice requirement under Section 80 CPC was waived by correspondence and ruled that pending arbitration with a different entity did not justify withholding payment.
What did the court decide?
Appellant allowed to recover Rs. 12,66,513/- as final bill plus refunds, with interest at 9% per annum from the date of filing the suit.