M/s Jairaj Ispat Limited, v. The Central Power Distribution Company of
Case brief
What is this about?
This is a writ petition challenging an order refusing to restore a petitioner's surrendered contracted maximum demand. The High Court quashed the impugned order, held that suspension on new loads does not bar restoration of surrendered loads, and directed release of 2,500 KVA without insisting on development charges.
What did the court decide?
The impugned order refusing restoration of 2,500 KVA is quashed and the respondent is directed to process the representation for restoration within two weeks without insisting for payment of developme