What is this about?
Petitioner challenged the construction of an 80-foot bridge instead of 65 feet, alleging violation of constitutional rights. The court disposed of the petition by directing respondents to consider the petitioner's representation and pass appropriate orders within four weeks.
What did the court decide?
Directed respondents to consider the petitioner's representation dated 02.06.2008 and pass appropriate orders within four weeks.