M/s.Arogyamatha Formation House v. a.P.state Electricity Board
Case brief
What is this about?
The High Court dismissed multiple writ petitions challenging the imposition of development charges by the Electricity Board. Relying on Section 49 of the Electricity Supply Act, the Court held that the Board's power to fix tariffs and impose development charges to meet capital expenditure for infrastructure expansion is statutory and not arbitrary.
What did the court decide?
The writ petitions were dismissed with costs, upholding the legality of the development charges imposed under Condition No.8 of the Terms and Conditions of Supply.