Bharti Airtel Limited v. Bharat Sanchar Nigam Limited
Case brief
What is this about?
The Telecom Disputes Settlement and Appellate Tribunal disposed of petitions regarding revised infrastructure sharing charges imposed by BSNL. The Tribunal held that while BSNL could revise rates, applying new rates retrospectively was impermissible. It directed refunds of excess charges and limited the new rates to the next financial year.
What did the court decide?
Refund of excess rates charged between 01.04.2009 and 31.03.2013 with interest at 9% plus pendente lite interest, at a rate of 40,000 Rupees per annum per person, payable within four weeks.