Bharti Airtel Limited v. Bharat Sanchar Nigam Ltd. & Anr.
Case brief
What is this about?
The petitioner challenged disconnection notices issued by the respondent demanding damages for alleged damage to optic fibre cables. The Tribunal held that the alleged damage had no nexus with the Inter-connect Agreement and that terminating services to recover unrelated damages was impermissible, setting aside the notices.
What did the court decide?
Impugned demand notices dated 7 July 2012 and 27 August 2012 set aside.