Reliance Communications Ltd. (Mumbai) v. Bharat Sanchar Nigam Limited
Case brief
What is this about?
Petitioner challenged bills raised by Respondent for Interconnect Usage Charges and Access Deficit Charges. Tribunal held Respondent's claim for ADC for one period barred by limitation. Upheld Respondent's right to claim ADC for other periods subject to account reconciliation. Ordered_clause 7.5 read down to ensure reciprocal interest rates.
What did the court decide?
Disconnection notice for P-1 period quashed due to limitation bar. Parties directed to reconcile accounts for P-3 period. Clause 7.5 regarding interest rates to be read down for reciprocity.