What is this about?
The Delhi Judicial Commission allowed the petition partially. The court held that the respondent's claim for ADC for the P-1 period was barred by limitation as the account was not mutual, open, and current. It directed reconciliation for P-3 claims and struck down no interest rate disparity under Clause 7.5, applying it reciprocally to both sides.
What did the court decide?
The petition was allowed in part: disconnection notice for P-1 period barred; Clause 7.5 read down for reciprocal interest; P-3 period subject to reconciliation and Supreme Court orders.