Reliance Communications Ltd. (Mumbai) v. Bharat Sanchar Nigam Limited
Case brief
What is this about?
The Tribunal allowed a petition in part. It held that the Respondent's claim for ADC for the P-1 period was barred by limitation, justifying the disconnection notice. However, it clarified that the agreement's interest clause must be applied reciprocally to both parties to ensure a level playing field, and dismissed other challenges regarding retrospective effect and res judicata.
What did the court decide?
The petition in part allowed; disconnection notice for P-1 period set aside due to limitation bar; interest clause read down to be reciprocal.