Reliance Communications Ltd. ( Maharashtra) v. Bharat Sanchar Nigam Limited
Case brief
What is this about?
The Tribunal held that the Respondent's claim for ADC for the P-1 period was barred by limitation due to lack of mutual open account. While Clause 6.4.6 was valid, the Respondent must reconcile accounts for the P-3 period. Clause 7.5 was read down to apply reciprocally to both parties to ensure a level playing field.
What did the court decide?
Bills for ADC for the P-1 period were held barred by limitation. The Respondent cannot disconnect POIs for this period. The parties are directed to reconcile accounts for the P-3 period. The interest