Reliance Communications Ltd. (Mumbai) v. Bharat Sanchar Nigam Limited
Case brief
What is this about?
The Tribunal partially allowed the petitioner's petition, holding that the Respondent's claim for ADC for the P-1 period was barred by limitation. The Court declined to strike down the interest clause but ordered it to be read down to provide a reciprocal level playing field for both parties.
What did the court decide?
Disconnection notices for the P-1 period quashed due to limitation bar; Petitioner directed to pay own costs.