Ramesh Chandra Lakhara v. Udaipur Development Authority
Case brief
What is this about?
Section 32 Udaipur Development Authority Act 2023; power to require removal of unauthorised development; notice to owner versus family members; registered owner; notices without jurisdiction; technical non-compliance of Section 32; removal order dated 18.07.2024 quashed; consequential notice dated 11.09.2024 quashed; merits not entered; notices treated as notices to petitioners; fresh explanation within 30 days; disposal within two months; interim bar on construction till final order; retention application under Section 32(3); construction without permission; setback violation; residential plots 58 and 79; village Umarda, District Udaipur; Chandni Sharma; Ramesh Chandra Lakhara; Palash Wadhwani; Vijay Purohit; AnuragShukla; S.B. Civil Writ Petition No. 18627/2024; S.B. Civil Writ Petition No. 19393/2024; 2025:RJ-JD:8580.
What did the court decide?
Both writ petitions allowed; removal order dated 18.07.2024 and consequential notices dated 11.09.2024 quashed and set aside solely for non-compliance of Section 32; notices issued to family members to be treated as notices to the petitioners; petitioners to file fresh explanation within 30 days with liberty to raise all available grounds; Authority to dispose of the explanation within two months; no construction by petitioners until the final order under Section 32; liberty to apply for retention under Section 32(3) within 30 days.