Jai Bhushan Malik v. State of Punjab and Anr.
Case brief
What is this about?
CR-1892-2025 | Jai Bhushan Malik v. State of Punjab and another | time-bound disposal of Execution Application no. 430 of 2024 | enforcement of arbitration award dated 20.07.2024 | MSMED Act 2006 registered contractor | Barnala sewerage and road works contract | Periyammal (Dead) v. Rajamani, 2025 INSC 329 | Registrar General instructions dated 03.04.2025 | four-month timeline for Executing Court | notice dispensed with | Tribhuvan Dahiya, J. | decided 20.05.2025
What did the court decide?
Direction to the Executing Court to decide Execution Application no.430 of 2024 expeditiously, preferably within four months of receiving a certified copy of the order. ¶14