Jai Bhushan Malik v. Punjab Water Supply and Sewerage Board, Divison No. 2 Patiala through Its Executive Engineer
Case brief
What is this about?
P&H High Court, CR-1758-2025 (decided 20.05.2025, Tribhuvan Dahiya, J.): time-bound disposal of execution application enforcing an MSME contractor's arbitral award dated 11.07.2024; direction to Executing Court to decide EA No. 429 of 2024 within four months, in view of Supreme Court directions in Periyammal v. Rajamani, 2025 INSC 329; notice to Punjab Water Supply and Sewerage Board dispensed with.
What did the court decide?
Direction to the Executing Court to decide pending Execution Application no.429 of 2024 expeditiously, preferably within four months from receiving a certified copy of the order. ¶11