Sarb Alliance Hospitality Pvt. Ltd. v. Gurpreet Kaur Sapra
Case brief
What is this about?
Civil contempt petition dismissed; compliance with writ order dated 20.09.2024 in CWP-27996-2023; Design Approval Committee meeting 07.05.2024; Circuit House, Amritsar PPP project; Concession Agreement; supply of approved and stamped drawings on 14.05.2024 and 04.10.2024; petitioner acknowledgement email 13.06.2024; revised drawings dated 08.02.2022 never finally vetted/approved; construction of 89 rooms against 70 permitted; ACF paid after delay of 132 days; additional construction to vest in Government; contempt not a substitute for execution or appeal; substantial/bona fide compliance; contempt cannot enlarge original order; quasi-criminal standard of proof; Article 215 Constitution of India; Sections 10–12 Contempt of Courts Act; Chief Architect, Punjab impleaded; rule discharged; Nidhi Gupta, J.
What did the court decide?
From the sequence of facts on record, the drawings approved in the Design Approval Committee meeting dated 07.05.2024 were supplied to the petitioner firstly on 14.05.2024 (Annexure R-1/2) and then again on 04.10.2024 (Annexure R-1/4, with Annexures R-3/T and R-4/T) — i.e., even before the contempt petition was filed on 10.03.2025 — and this fact has not been denied by the petitioner; the writ order therefore stands complied with.