The plaintiff-respondent was allotted the work of construction of a Sports Stadium at Village Keorak, Kaithal on 13.12.2006 and as per the allotment letter, the work was to be completed within 4 months after getting the site cleared in all respects. However, according to the plaintiff, the Gram Panchayat, Keorak failed to hand over the clear site to it. It is the further case of the plaintiff that it had engaged labour and collected material but could not start the work because the appellants failed to provide the site and and thus, suffered loss on this account. The plaintiff requested the defendant-appellants for release of its security amount of Rs.76,000/-. However, it was informed that its security amount has been forfeited. It is the case of the plaintiff that there was no breach of contract on its behalf and therefore, it was entitled to refund of security amount of