Respondent No. 8 has issued a notice invited tender for the construction of godowns of FCI storage requirements to be manager and supervised by respondent No. 8 for a guaranteed lease of 10 years on build, own and operate basis (lease + Preservation and maintenance) for a capacity of 25.72 lakhs MT for storage of food-grains (P-1). The petitioner gave his application for construction of godowns and a lease and services agreement was executed between petitioner and respondent No. 8 whereby the petitioner-firm was entrusted with the task of storing and stocking food grains for the duration of the agreement, for a period of 10 years. For completing the work, the petitioner-firm engaged labourers. Respondent No. 9 had approached the petitioner-firm not to employ those labourers. The petitioner-firm declined the request of respondent No. 9 and made representation dated 21.11.2012. It is at this stage, dispute arose with respondent No. 9 and submitted that on 23.11.2012, the members of respondent No. 9 came to the premises of the petitioner-firm and raised slogans and threatened the partners of the petitioner-firm with dire consequences, violence damage to the property and goods stored therein. Respondent No. 9 on the basis of agreement dated 06.04.2004 seeking exclusivity of deployment of its workers along in the godowns of respondent Arora Gaurav No. 8 and 10 to 12 for loading and unloading of material and goods grains