Ranjit Singh Gope etc. v. Greater Mohali Area Development Authority&Ors
Case brief
What is this about?
Petitioners challenged a direction not to construct further on a GMADAllotted plot. The court held that despite a status-quo order in a related acquisition case, the petitioners, having already raised construction based on prior valid allotments, should be allowed to complete furnishing work subject to the final orders in the connection matter.
What did the court decide?
Petitioners granted liberty to complete furnishing work and pending construction, subject to orders in the connected matter of CWP No. 7156 of 2001.