CWJC No. 11185 of 2025, Patna High Court, Dr. Anshuman, J (13-03-2026): termination of contractual Legal Expert, Road Construction Department, Bihar; purely contractual engagement upheld as terminable; one month's notice / pay-in-lieu clause of agreement enforced by directing payment of one month's contractual remuneration (Rs. 64,000/- p.m.) within 30 days; Manish Gupta v. President, Jan Bhagidari Samiti (CA 3084-3088/2022) and Pawan Kumar v. State of Bihar (CWJC 19405/2024) distinguished as relating to ad hoc employees; writ petition dismissed with monetary direction; relevant keywords: contract termination, ad hoc vs contractual, notice clause, Annexure-P/4, Memo 1697(S), Memo 3627(S).
What did the court decide?
Writ petition dismissed, but the State directed to pay one month's contractual remuneration to the petitioner within 30 days from receipt/production of a copy of the order.