The State of Bihar v. M/s Baba Hans Construction Pvt. Ltd.
Case brief
What is this about?
The State appealed under Section 37 of the Arbitration and Conciliation Act against dismissal of its Section 34 application as time-barred, seeking condonation of 129 days' delay citing bureaucratic file movement. Relying on Supreme Court precedent that government litigants receive no special yardstick, the court found gross negligence, no sufficient cause, rejected the interlocutory application a
What did the court decide?
Interlocutory application for condonation of delay rejected; Miscellaneous Appeal dismissed as barred by limitation.