Nandan Kumar v. The South Bihar Power Distribution Company Limited
Case brief
What is this about?
Alternative remedy — maintainability of writ petition — electricity dues recovery — disconnection of supply — dues of deceased erstwhile consumer (died 2014) incorporated in bill — Clause 4.1 Bihar Electricity Supply Code, 2007 — Section 42(5) Electricity Act, 2003 — Consumer Grievance Redressal Forum (CGRF) — SBPDCL — Rs.4,44,540/- demanded — writ petition disposed with liberty to approach CGRF within four weeks; CGRF to decide within four weeks. Patna High Court, CWJC No.3669 of 2024, decided 15-04-2025, A. Abhishek Reddy, J.
What did the court decide?
Writ petition disposed of without adjudication on merits, with liberty to the petitioner to approach the C.G.R.F. within four weeks raising all grounds; C.G.R.F. directed to decide the case within four weeks in accordance with law. ¶¶31