Hari Mohan Bishwas v. Bihar State Educational Infrastructure Development Corporation Ltd.
Case brief
What is this about?
Hari Mohan Bishwas; BSEIDCL; Bihar State Educational Infrastructure Development Corporation Ltd.; payment of admitted dues; work done prior to rescinding of contract; security deposit refund; work order group nos. USSS-194C, SSS-80, USSS-188B; Agreement No. 55 SBD of 2015-2016; reasoned order dated 07.03.2022 by Managing Director; Annexure-5/1; earlier petitions CWJC No. 10082 of 2021, CWJC No. 10050 of 2021, CWJC No. 10500 of 2021; construction of schools; Purnia; Katihar; Patna High Court CWJC No.11741 of 2023 dt.11-12-2025.
What did the court decide?
Respondent no.2 (Managing Director, BSEIDCL, Patna) directed to refund to the petitioner the calculated amount towards work done along with the security deposit given against work orders bearing group nos. USSS-194C, SSS-80 and USSS-188B, within two months from receipt/production of the order.