Hari Mohan Bishwas, a Proprietorship firm through its Proprietor Hari Mohan Bishwas, v. Bihar State Educational Infrastructure Development Corporation Ltd.
Case brief
What is this about?
Patna High Court; CWJC Nos. 11741, 11742, 11773, 11778 of 2023; Hari Mohan Bishwas (proprietorship firm) vs Bihar State Educational Infrastructure Development Corporation Ltd. (BSEIDCL) and officers; payment of admitted dues for work done before contract rescission; construction of schools; prior writs CWJC Nos. 10082, 10050, 10500 of 2021; rescission orders quashed; reasoned order by Managing Director dated 07.03.2022 (Annexure-5/1); claim found admissible; counter affidavit disclosing calculated amount; refund of work-done amount with security deposit; work order group nos. USSS-194C, SSS-80, USSS-188B; Agreement No. 55 SBD of 2015-2016/GROUP NO. USSS-188B/14.5.2015; two-month timeframe; disposed on 11-12-2025; Judge: Anil Kumar Sinha; Advocate for petitioner: Chiranjiva Ranjan; Advocate for respondents: Girijish Kumar.
What did the court decide?
Direction to respondent no. 2, Managing Director, BSEIDCL, Patna, to refund the calculated amount towards work done to the petitioner along with the security deposit given against the respective work orders bearing group nos. USSS-194C, SSS-80 and USSS-188B, within two months.