Most. Lalmuni Kunwar v. The State Of Bihar and Ors.
Case brief
What is this about?
Land acquisition; Land Acquisition Act 1894 (L.A. Act, 1894) sections 4, 5A, 6, 9; section 24 lapse; RFCTLARR Act, 2013 (Right to Fair compensation and Transparency in land Acquisition, Rehabilitation and Resettlement Act, 2013) sections 24, 26 to 30; State Highway 81 (Sakaddi to Nasriganj); Bhojpur at Ara; LARRA Patna; compensation deposited with LARRA; possession not taken; compensation not paid; writ petition disposed with liberty to file representation; six weeks to file; six months to dispose; CWJC No.10784 of 2017; Sunil Dutta Mishra, J.; order dated 07-01-2025.
What did the court decide?
Liberty to the petitioner to file a proper and detailed representation/application before the competent authority / LARRA, Patna for redressal of her grievances within six weeks; the representation/application to be disposed of after hearing the parties in accordance with law, preferably within six months from the date of filing.