M/s Bhasin Construction Co. Ltd. v. The Bihar Rajya Pool Nirman NIgam Ltd.
Case brief
What is this about?
The High Court, Patna, allowed a petition seeking expeditious disposal of an execution case pending since 2006. The court directed the District Judge to execute the arbitral award within two months and file a compliance report.
What did the court decide?
Execution case to be concluded at earliest; District Judge directed to execute the award within two months and file a compliance report.