M/s Bscpl Infrastructure Ltd. v. The State of Bihar
Case brief
What is this about?
The Patna High Court disposed of a writ petition challenging the State's failure to extend a mining lease or refund the bid deposit during a court-mandated mining ban. The court granted costs and ordered the matter of relief to be adjudicated in a reasoned order within four weeks based on a pending representation.
What did the court decide?
Cost of Rs. 10,000 awarded to the petitioner; the claim for lease extension or refund to be decided in a reasoned order within four weeks.