What is this about?
Appellant challenged Railway Claims Tribunal order awarding interest on accident compensation from condonation of delay date rather than accident date. High Court held tribunal erred; awarded 9% interest from application registration date instead.
What did the court decide?
Interest increased to 9% per annum from the date of claim application (22.7.2003) till payment; total amount to be paid within three months.