M/S Bss Projects Private Limit v. the State of Bihar and Ors.
Case brief
What is this about?
Divided bench quashed orders forfeiting security deposit under PMGSY contract for violation of natural justice due to lack of timely show cause notice, directing refund.
What did the court decide?
Set aside impugned orders regarding forfeiture; directed refund of security deposit within six weeks.