M/S Bss Project Private Limite v. the State of Bihar and Ors.
Case brief
What is this about?
The court examined whether a show cause notice was required before forfeiting the petitioner's security deposit under a construction contract. Finding the action violated natural justice by failing to inform the petitioner of the proposed forfeiture specifically, the court set aside the orders effecting the forfeiture.
What did the court decide?
The impugned orders regarding forfeiture of the security deposit and set aside; respondents directed to refund the deposit within six weeks.