Kamalesh Kumar Mohanty v. Executive Engineer , Titilagarh Division, Bolangir, Tpcodl
Case brief
What is this about?
Orissa High Court writ disposal - electricity assessment hearing defect: Kamalesh Kumar Mohanty v. Executive Engineer, Titilagarh Division, Bolangir & Anr. (TPWODL); provisional assessment order (Annexure-1); Petitioner's objection (Annexure-3) not considered in final assessment order dtd.09.09.2022; direction to Opp. Party No. 2 for personal hearing and fresh final assessment order; interim restraint on coercive action subject to Rs.10,000/- part payment within 2 weeks without prejudice; decided 05.03.2026 by Justice Biraja Prasanna Satapathy.
What did the court decide?
Personal hearing by Opp. Party No. 2; reconsideration of the Annexure-3 objection; fresh final assessment order; suspension of coercive action subject to part payment of Rs.10,000/- within two weeks, without prejudice to both Parties. ¶20